AL HB518
Bill
Status
5/24/2011
Primary Sponsor
Ronald Johnson
Click for details
AI Summary
HB518 Summary
-
Amends Alabama Code Section 8-29-3 to define retainage in construction contracts and establish requirements for retainage payments across owner-contractor-subcontractor chains.
-
Increases maximum retainage percentage from 5% to 10% of estimated work value, with no further retainage withheld after 50% project completion.
-
Requires owners to release and pay retainage to contractors within 60 days after contractor's work completion or substantial project completion (whichever occurs first), with all certificates of occupancy issued.
-
Imposes 1% monthly interest (12% annually) on retainage amounts withheld in excess of permitted limits and on any retainage not paid on time.
-
Applies only to construction contracts entered into on or after the effective date; becomes effective the first day of the third month following passage and Governor approval.
Legislative Description
Construction contracts, retainage requirements, defined, Sec. 8-29-3 am'd.
Contracts
Last Action
Pending third reading on day 28 Favorable from Commerce, Transportation, and Utilities
5/31/2011