AL SB237
Bill
AI Summary
SB237 Summary
-
Requires pre-bid meetings for public works contracts to be held at least 7 days prior to bid opening, with exemption for road and bridge projects.
-
Prohibits modification of project specifications within 24 hours before bid opening, except for road and bridge projects.
-
Reduces payment timeframe from 45 days to 35 days after awarding authority designee approves completed work, with designated person required to review work within 10 days.
-
Establishes procedures for disputing submitted invoices, requiring written notice of disapproval within 10 days with reasons and dispute resolution procedures specified.
-
Allows contract term alterations when subsurface or unknown physical conditions materially differ from contract specifications, with architect/engineer investigation and recommendation required within 10 days of discovery.
-
Exempts road, bridge, and highway projects from prompt payment contract requirements and pre-bid meeting timeframe rules.
Legislative Description
Contracts, payment of state contractors, state may not increase time for payment beyond 30 days, time frame to hold pre-bid meetings specified, review of invoices in specified time frame required, alteration of contract allowed under certain circumstances, Sec. 39-2-2, 39-2-12 am'd.
State Agencies
Last Action
Pending third reading on day 29 from Transportation, Utilities and Infrastructure
5/7/2013