AL HB547
Bill
Status
3/13/2014
Primary Sponsor
John Rogers
Click for details
AI Summary
-
Requires contractors to timely pay subcontractors for work completed on public works contracts within 7 days of the contractor receiving payment from the owner, or per agreed terms if specified in the contract.
-
Mandates contractors pay subcontractors within 10 business days of receiving funds for public works projects, superseding the standard 7-day requirement.
-
Establishes that retainage (money withheld from payments) cannot exceed 10 percent of estimated work value, with no further retainage after 50 percent project completion.
-
Imposes a 1 percent per month (12 percent per annum) interest penalty on any party that fails to make timely payments or withholds retainage in excess of the allowed limits.
-
Becomes effective on the first day of the third month following passage and approval by the Governor.
Legislative Description
Contractors, public works contracts, timely payments, contractor required to timely pay a subcontractor for work completed, Sec. 8-29-3 am'd.
Contractors
Last Action
Pending third reading on day 27 Favorable from Fiscal Responsibility and Accountability
3/19/2014