AL SB459

Bill

Status

Passed

6/2/2015

Primary Sponsor

Steve Livingston

Click for details

Origin

Senate

Regular Session 2015

AI Summary

SB459 Summary

  • Requires permit from local DeKalb County governing body (county commission or municipal council) before constructing, installing, or operating a wind energy conversion system for power resale purposes.

  • Property must be appropriately zoned and systems must be certified by a licensed engineer with wind energy experience to meet good engineering practices and all building and electrical codes.

  • Establishes design and safety requirements including manual and automatic overspeed controls, 40-decibel noise limit at property line, 2,500-foot encroachment buffer from adjacent properties, and unclimbable tower design with anti-climbing devices or fencing.

  • Applicant must maintain $1,000,000 liability insurance plus financial assurance covering reclamation and removal costs; local governing body collects $1,000 permit fee plus all review costs including engineering, inspection, and attorney fees.

  • Systems inactive for 365 consecutive days may be deemed abandoned and removed by operator; permit holder can request delay by proving system will become operable.

Legislative Description

DeKalb Co., wind energy conversion systems, permitting and regulation of by municipal governing body or county commission, certification by licensed engineer required, regulation of location, design, and operation of systems

DeKalb County

Last Action

Assigned Act No. 2015-387.

6/2/2015

Committee Referrals

Local Legislation5/26/2015
Local Legislation5/7/2015