Adds section 14-235-226 to Arkansas Code establishing procurement procedures for municipal sewage systems, including definitions and authorization for alternative project delivery methods.
-
Defines "design-build" as a two-step procurement process where a municipal sewage system acquires both design and construction services from a single entity based on qualifications first, then best value (lowest capital cost, lowest life-cycle cost, or combination thereof).
-
Authorizes municipal sewage systems to use design-build construction for projects exceeding $2,000,000 if they employ or contract with a licensed professional engineer for project-scope development and construction oversight.
-
Authorizes municipal sewage systems to use general contractor construction management as a project delivery method for projects of any amount, with the general contractor providing preconstruction services and then serving as the general contractor with a maximum guaranteed price.
-
Requires design-builders to contract directly with subcontractors and be responsible for project bonding, and mandates all projects using these methods comply with state and federal law.
Legislative Description
Concerning Procurement Procedures For Municipal Sewage Systems.
Last Action
Notification that HB1645 is now Act 627