- Increases the number of transportation projects authorized under the Construction Manager-General Contractor Method Pilot Program from three (3) to five (5) projects
- Raises the total construction cost cap for all five projects from an unspecified amount to $200,000,000, with the first project capped at $70,000,000 and remaining projects capped at $100,000,000
- Extends the program termination date from June 30, 2022 to June 30, 2024
- Changes legislative findings to reflect that the State Highway Commission "has developed" rather than "is interested in developing" an alternative cost-effective procurement procedure
- Clarifies that the Arkansas Department of Transportation shall establish procedures for awarding construction manager-general contractor method contracts based on criteria listed in Arkansas Code § 19-11-1406
Legislative Description
To Amend The Construction Manager-general Contractor Method Of Procurement Pilot Program.
Last Action
Notification that HB1693 is now Act 1019
4/15/2019
Committee Referrals
Public Transportation4/8/2019
Transportation, Technology & Legislative Affairs3/19/2019
Public Transportation3/5/2019