AZ SB1403
Bill
Status
2/14/2018
Primary Sponsor
Sonny Borrelli
Click for details
AI Summary
-
Reduces payment retention on public works construction contracts from 10% to 5% of project costs for state agencies, counties, and municipalities.
-
Requires payment of progress estimates within 14 days after certification and approval, with automatic approval after 7 days unless owner issues written findings detailing reasons for non-approval.
-
Establishes contractor and subcontractor rights to suspend work or terminate contracts for non-payment, with notice requirements (3-7 days depending on circumstances).
-
Requires contractors to pay subcontractors within 7 days of receiving payment, prohibits withholding retention exceeding amounts retained by owner, and mandates 1% monthly interest on late payments to subcontractors.
-
Voids contract provisions that prevent suspension or termination for non-payment, require disputes be resolved outside Arizona, or materially limit contractor recovery for delays caused by the owner.
Legislative Description
Construction contracts; public works; payments
Repeal
Last Action
Senate GOV Committee action: Discussed and Held, voting: (0-0-0-0)
2/14/2018