AB 228 Summary
-
Increases the net energy metering capacity limit from 5% to 6% of an electric utility's aggregate customer peak demand, with 1% reserved for large commercial or industrial customer-generators until January 1, 2016.
-
Expands eligible customer-generator facility capacity from 1 megawatt to 5 megawatts for solar, wind, or hybrid electrical generating systems.
-
Requires electricity fed back to the grid by large commercial or industrial customer-generators to not offset charges for transmission and distribution services.
-
Extends the interconnection agreement processing timeline from 30 working days to 90 working days for large commercial or industrial customer-generators and requires these customers to pay for interconnection studies and upgrades.
-
Repeals Section 2827.5 and makes conforming changes to wind energy co-metering provisions in Section 2827.8.
Legislative Description
Electricity: net energy metering.
Last Action
From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on E., U., & C.