CA SB1109

Bill

Status

Passed

9/16/2022

Primary Sponsor

Anna Caballero

Click for details

Origin

Senate

2021-2022 Session

AI Summary

  • Extends the deadline for electrical corporations to collectively procure 125 megawatts from existing bioenergy projects from December 1, 2016 to December 31, 2023, with financial commitments of 5 to 15 years.

  • Requires at least 80 percent of bioenergy facility feedstock to come from sustainable forestry management, with at least 60 percent from Tier 1 and Tier 2 high hazard zones designated by the Department of Forestry and Fire Protection.

  • Exempts certain local publicly owned electric utilities from procurement requirements if they previously entered into 5-year financial commitments and have contracts with facilities in bankruptcy or projects not delivering energy to them.

  • Requires all new bioenergy contracts or extensions of 5 years or longer to meet emission limits equivalent to or more stringent than the applicable best available retrofit control technology as determined by local air districts.

  • Extends the biomass contract renewal requirement from December 31, 2023 to December 31, 2028, requiring entities to seek amendments adding 5 additional years to expiring contracts.

Legislative Description

California Renewables Portfolio Standard Program: bioenergy projects.

Last Action

Chaptered by Secretary of State. Chapter 364, Statutes of 2022.

9/16/2022

Committee Referrals

Appropriations6/29/2022
Utilities and Energy6/9/2022
Appropriations5/3/2022
Energy, Utilities and Communications3/23/2022