CA SB1174

Bill

Status

Passed

9/2/2022

Primary Sponsor

Bob Hertzberg

Click for details

Origin

Senate

2021-2022 Session

AI Summary

  • Requires electrical corporations to annually report to the Public Utilities Commission on changes to in-service dates of transmission and interconnection facilities for renewable energy and energy storage resources with executed interconnection agreements, identifying reasons for any delays.

  • Requires the PUC's annual legislative report on renewable energy compliance to include a systemwide assessment of delays to interconnection or transmission approvals for renewable energy and energy storage resources.

  • Adds transmission to the list of factors the PUC must consider when reviewing integrated resource plans to ensure load-serving entities meet energy and reliability needs while reducing the need for new generation and transmission resources.

  • Approved by Governor September 2, 2022; contains no state reimbursement requirements for local agencies or school districts.

Legislative Description

Electricity: eligible renewable energy or energy storage resources: transmission and interconnection.

Last Action

Chaptered by Secretary of State. Chapter 229, Statutes of 2022.

9/2/2022

Committee Referrals

Appropriations6/23/2022
Utilities and Energy6/2/2022
Appropriations4/5/2022
Energy, Utilities and Communications3/2/2022
Rules2/17/2022

Full Bill Text

No bill text available