CA AB941
Bill
Status
2/2/2026
Primary Sponsor
Rick Zbur
Click for details
AI Summary
-
Requires the Public Utilities Commission to make a final determination on environmental review for priority electrical infrastructure projects within 270 days of deeming an application complete
-
Defines "priority projects" as electrical transmission projects approved by the Independent System Operator, projects interconnecting renewable generation to the grid, system upgrades in ISO cluster studies, or substations needed to support electrification-related load growth
-
Commission staff must review applications within 30 days of filing and notify applicants of any deficiencies; applicants have 60 days to correct deficiencies or explain why they cannot
-
The 270-day timeline may be extended if the environmental impact report requires recirculation, substantial project changes occur, new significant information emerges, or additional time is needed for wildlife or water board surveys due to seasonal constraints
-
Applicants must identify whether their project qualifies as a priority project and provide the basis for that designation in their application
Legislative Description
California Environmental Quality Act: electrical infrastructure projects.
Last Action
From committee: Filed with the Chief Clerk pursuant to Joint Rule 56.
2/2/2026