AI Summary
-
Extends the timeframe for the Department of Energy and Environmental Protection to identify and notify applicants of application deficiencies from sixty days to ninety days after receiving an application for a permit.
-
Changes the department's obligation from making "all reasonable efforts" to ensure notification to a mandatory requirement that the department "shall" notify applicants of deficiencies in writing.
-
Applies to commercial project permit applications reviewed by the department, allowing the schedule to reasonably limit the time applicants have to remedy identified deficiencies.
-
Effective October 1, 2017, amending section 22a-6p(b)(2) of the general statutes.
Legislative Description
An Act Requiring The Department Of Energy And Environmental Protection To Notify Commercial Project Applicants Of Deficiencies Within Ninety Days.
Last Action
File Number 51