FL H0353
Bill
Status
4/28/2015
Primary Sponsor
Daniel Burgess
Click for details
AI Summary
-
Florida Public Service Commission prohibited from authorizing advanced cost recovery for more than one power plant by any utility at any one time.
-
Commission required to conduct quarterly reviews of utilities collecting advanced costs to ensure continued progress toward siting, design, licensing, or construction of the power plant.
-
Utility must petition commission within 10 years of obtaining nuclear regulatory license or certification to preserve cost recovery opportunity; commission determines if utility intends to build the plant.
-
If utility lacks intent to build after 10-year deadline or cannot complete construction within 20 years of license/certification, commission must order refund of all previously collected costs to customers.
-
Act takes effect July 1, 2015.
Legislative Description
Advanced Cost Recovery
Last Action
Died in Energy and Utilities Subcommittee
4/28/2015