HB 395 Summary

  • Expires advanced cost recovery provisions for nuclear and integrated gasification combined cycle power plants on July 1, 2016, with section repealed July 1, 2017.

  • Requires utilities to return all costs collected under advanced cost recovery to ratepayers by June 30, 2017, and prohibits utilities from charging new fees, increasing fees, or raising rates to offset lost revenues from refunding collected costs.

  • Amends securitization eligibility to exclude costs claimed for recovery under section 366.93 unless they were already in the utility's rate base and included in base rates before plant retirement or abandonment.

  • Deletes provisions that limited challenges to a utility's right to recover pre-commercial operation costs for nuclear or integrated gasification combined cycle power plants.

  • Establishes that proceeding with plant construction following commission approval of need does not constitute evidence of imprudence, and cost increases beyond utility control are not deemed imprudent.

Legislative Description

Utility Advanced Cost Recovery

Last Action

Died in Energy and Utilities Subcommittee

3/11/2016

Committee Referrals

Energy And Utilities Subcommittee10/30/2015

Full Bill Text