AI Summary
-
Adds definition of "design-build" to Hawaii Revised Statutes as a project delivery method involving a single contract for design and construction.
-
Allows construction projects to be procured through competitive sealed proposals using the design-build method, subject to specific requirements.
-
Requires procurement officers to issue a request for proposals to prequalify offerors and select a short list of no more than three responsible offerors before final proposal submission.
-
Authorizes procurement officers to pay a conceptual design fee to non-selected offerors that submit technically responsive proposals for projects costing more than $1,000,000.
-
Takes effect July 1, 2011.
Legislative Description
Procurement; Design-Build Contracts
Last Action
(H) Act 211, on 7/11/2011 (Gov. Msg. No. 1315).