Requires Land Use Commission to conduct additional review of permit plan applications for wind turbines generating more than 100 kilowatts of energy located within three-quarters of a mile of residential, school, hospital, or business property lines
-
Land Use Commission, in coordination with the energy resources coordinator, must consider potential community impacts and conformity with existing state and county land use policies during the special review
-
Exempts wind turbine permit plan applications approved before July 1, 2015 from the additional review requirements
-
Applies the same definition of "wind turbine" as found in existing statute section 201N-31
-
Takes effect on July 1, 2030