HI SB1067
Bill
AI Summary
-
Allows bidders on public works construction projects two working days after bid closing to submit the names and scope of work for required joint contractors or subcontractors.
-
Delays bid opening for construction projects to no sooner than two working days after the bid closing deadline to accommodate subcontractor information submission.
-
Permits acceptance of construction bids missing subcontractor listings if the work value is 1% or less of total bid amount and acceptance is in the State's best interest.
-
Addresses bid challenges and project delays caused by technical errors in subcontractor listings and licensing scope issues that previously resulted in awards to non-lowest bidders.
Legislative Description
Relating To Procurement.
Procurement
Last Action
The committee on GVO deferred the measure.
2/9/2017