HI SB929
Bill
Status
1/22/2021
Primary Sponsor
Glenn Wakai
Click for details
AI Summary
-
Requires the Public Utilities Commission to approve, approve with modification, or disapprove renewable energy power purchase agreement applications within 180 days of filing, effective July 1, 2021; applications are deemed approved if no decision is rendered within this timeframe.
-
Mandates electric public utilities complete interconnection design and file interconnection or transmission line approval requests with the PUC within 270 days of the renewable energy project power purchase agreement filing.
-
Requires the PUC to approve or disapprove interconnection or transmission line requests within 120 days of filing; requests are deemed approved if no decision is made within this timeframe.
-
Allows electric utilities and renewable energy developers to mutually consent to extend interconnection completion timelines without affecting other projects.
-
Applies only to utility-scale renewable energy projects of 5 megawatts or larger requiring PUC interconnection approval, and does not apply to member-owned cooperative electric utilities.
Legislative Description
Relating To Renewable Energy.
Public Utilities Commission
Last Action
Report adopted; Passed Second Reading, as amended (SD 1) and referred to CPN/WAM.
2/18/2021