HI HB1612
Bill
Status
1/21/2022
Primary Sponsor
Scott Nishimoto
Click for details
AI Summary
HB 1612 Summary
-
Requires the Public Utilities Commission to develop and adopt reliability standards and interconnection requirements to facilitate timely interconnection of utility-scale renewable energy projects of 5 megawatts or larger.
-
Mandates electric utilities complete interconnection design, reach agreement with renewable energy developers, and file for interconnection approval within 270 days of a power purchase agreement filing, with interim status reports required at 90 and 180 days.
-
Requires the commission to approve or disapprove interconnection requests within 120 days of filing.
-
Imposes financial penalties on utilities that fail to meet the 270-day deadline by requiring forfeiture of performance incentive mechanism funds and awards related to the renewable energy project.
-
Requires the commission to report to the governor and legislature within 30 days of any utility failure to meet interconnection timing requirements.
Legislative Description
Relating To Renewable Energy.
Renewable Energy
Last Action
Referred to EEP, CPC, FIN, referral sheet 2
1/26/2022