AI Summary
-
Requests the Public Utilities Commission order Hawaiian Electric to continue deployment of community-based renewable energy projects through Phase 2, Tranche 2 of the Community-Based Renewable Energy Program.
-
Directs the Public Utilities Commission to order Hawaiian Electric to revoke the suspension of procurement and continue issuing requests for proposals for the Community-Based Renewable Energy Program.
-
Notes that approximately five community-based renewable energy projects have been installed since 2015, with thirteen projects in Phase 2, Tranche 1 scheduled for installation from 2024 to 2026.
-
States that community-based renewable energy projects allow residents unable to afford solar systems or those in condominiums to access renewable energy and lower electric bills without large upfront investments.
-
Argues Hawaiian Electric has had sufficient time (more than eight years) to implement the program and does not require additional delays, rejecting the utility's recommendation to pause Phase 2, Tranche 2.
Legislative Description
Requesting The Public Utilities Commission To Order Hawaiian Electric To Continue To Deploy And Pursue Community-based Renewable Energy Projects.
Hawaiian Electric
Last Action
Report adopted; referred to the committee(s) on CPC with none voting aye with reservations; Representative(s) Garcia voting no (1) and Representative(s) Evslin, Garrett, Kila, Lamosao, Martinez, Nakashima, Quinlan excused (7).