HI SB1587
Bill
Status
1/23/2025
Primary Sponsor
Henry Aquino
Click for details
AI Summary
-
Amends Hawaii Revised Statutes Section 103-32.1(c) to allow procurement officers to withhold retainage fees from the total project budget (rather than only from amounts due to contractors) to ensure proper contract performance.
-
Removes the previous requirement that retainage withholding stop after 50% contract completion if progress is satisfactory, simplifying the retainage framework.
-
Requires retainage fees to be paid to contractors within a specified number of days after 100% contract completion, including all amendments, supplementary contracts, certificates, inspections, and warranty periods.
-
Defines "total project budget" as the contract amount which may be increased or decreased through contract amendments and supplementary contracts.
-
Applies to all public contracts executed on or after January 1, 2026.
Legislative Description
Relating To Retainage.
Contractors
Last Action
Report adopted; Passed Second Reading, as amended (SD 1) and referred to WAM.