HI HCR203
Concurrent Resolution
Status
3/16/2026
Primary Sponsor
Nicole Lowen
Click for details
AI Summary
-
Requests the Public Utilities Commission to provide a written status update on implementing the Hawaii Electric Reliability Administrator (HERA), established by statute in 2012 to oversee electric system reliability standards and interconnection functions.
-
Notes that as of March 2026, HERA has not been fully implemented despite Act 201 (2022) requiring a comprehensive study on interconnection accessibility, and over 50% of renewable energy projects have been canceled before achieving commercial operations.
-
Identifies projected capacity shortfalls on Maui and Hawaii islands in 2028, with reliability contingency measures potentially requiring continued operation or life-extension of fossil fuel generating facilities.
-
Requires the Commission's status update to include: specific HERA functions committed to after Act 201, current implementation status, reasons for delays, and a forecasted timeline for full implementation.
-
Requests annual reports to the Legislature no later than 20 days before each regular session until HERA is fully implemented.
Legislative Description
Requesting The Public Utilities Commission To Provide A Written Status Update On The Implementation Of The Hawaii Electric Reliability Administrator.
Energy
Last Action
Offered