  • Iowa Utilities Commission granted supervisory authority over electric transmission line construction, operation, maintenance, and land restoration compliance inspections
  • Applies only to initial construction of transmission lines with voltage of 200 kilovolts or more outside city limits
  • Electric transmission owners must repair damaged underground drain tiles during and after construction to at least equal quality, size, and flow capacity
  • Agricultural land must be deep tilled at least 18 inches for cropland and 12 inches for other land to alleviate soil compaction from heavy equipment
  • Transmission owners must remove non-native rocks larger than 3 inches from easement areas and restore soil conservation practices, structures, and vegetation to pre-construction conditions

Legislative Description

A bill for an act relating to land restoration following the initial construction of electric transmission lines.(See HF 2227.)