Allows public utilities to apply for expedited review of certificates for new high voltage electric service lines not exceeding 5 miles in length and not advancing contiguously to projects filed in 2012.
-
Requires applicants to submit detailed engineering data, project descriptions, location maps, and identify a primary right-of-way plus alternate routes; applicants must pay a $100,000 application fee.
-
Mandates utilities hold minimum 3 pre-filing public meetings in each affected county with newspaper notice published weekly for 3 consecutive weeks, and establish a dedicated project website.
-
Commission must issue a decision within 150 days of filing, extendable by 75 additional days upon finding good cause before day 30.
-
Prohibits transmission line construction within 1.5 miles of 30 specified areas including residential zones, schools, parks, wetlands, airports, and archaeological sites; utilities must pay $20,000 per mile construction fee to affected counties.