IL SB1726
Bill
AI Summary
-
Utilities seeking to construct high-voltage electric service lines (100,000+ volts) must hold minimum 2 pre-filing public meetings in each affected county, with notice published weekly for 3 consecutive weeks beginning at least one month prior to the first meeting.
-
Utilities may apply for expedited certificate review under Section 8-406.1, requiring a $100,000 application fee, detailed engineering specifications, and proof of holding minimum 3 pre-filing public meetings in each affected county.
-
Commission must issue a decision on expedited applications within 150 days of filing, extendable by 75 additional days if good cause is found within 30 days of application.
-
Utilities granted certificates must pay counties $20,000 per mile of constructed high-voltage line within 30 days of project completion, in lieu of standard permitting fees.
-
Commission must notify affected property owners by registered mail of hearing times and locations for both standard and expedited certificate applications.
Legislative Description
UTILITY-HIGH-VOLTAGE ELEC LINE
Last Action
Public Act . . . . . . . . . 99-0399
8/18/2015