IL SB1726

Bill

Status

Passed

8/18/2015

Primary Sponsor

Chapin Rose

Click for details

Origin

Senate

99th General Assembly

AI Summary

  • Utilities seeking to construct high-voltage electric service lines (100,000+ volts) must hold minimum 2 pre-filing public meetings in each affected county, with notice published weekly for 3 consecutive weeks beginning at least one month prior to the first meeting.

  • Utilities may apply for expedited certificate review under Section 8-406.1, requiring a $100,000 application fee, detailed engineering specifications, and proof of holding minimum 3 pre-filing public meetings in each affected county.

  • Commission must issue a decision on expedited applications within 150 days of filing, extendable by 75 additional days if good cause is found within 30 days of application.

  • Utilities granted certificates must pay counties $20,000 per mile of constructed high-voltage line within 30 days of project completion, in lieu of standard permitting fees.

  • Commission must notify affected property owners by registered mail of hearing times and locations for both standard and expedited certificate applications.

Legislative Description

UTILITY-HIGH-VOLTAGE ELEC LINE

Last Action

Public Act . . . . . . . . . 99-0399

8/18/2015

Committee Referrals

Public Utilities5/13/2015
Rules5/7/2015
Energy and Public Utilities3/11/2015
Assignments2/20/2015