MD HB900
Bill
Status
1/30/2025
Primary Sponsor
C.T. Wilson
Click for details
AI Summary
-
Electric companies must submit a specific rate schedule for data centers with monthly maximum demand exceeding 2,500 kilowatts to the Public Service Commission for approval by July 1, 2026
-
Service contracts require a minimum initial term of 20 years plus a load ramp period of up to 4 years, with customers financially responsible for minimum charges even if they curtail or terminate service early
-
Data center customers must provide a guarantee or collateral equal to 50% of total minimum charges for the full contract term, unless they have credit ratings of at least A- (S&P) and A3 (Moody's) plus cash reserves exceeding 10 times the collateral requirement
-
Load ramp capacity requirements mandate data centers reach at least 50% of contract capacity in year 1, increasing to 90% by year 4, with minimum monthly billing demand set at 90% of contract capacity
-
Customers canceling or delaying projects by more than 12 months before the target service date must reimburse electric companies for 100% of buildout costs
Legislative Description
Electricity - Data Centers - Rate Schedule and Requirements
Rules and Regulations
Last Action
Hearing 2/20 at 1:00 p.m.
2/4/2025