Unsuccessful offerors may request a debriefing from the procurement officer on contract award decisions, which must be provided before the award is presented for final approval
-
Contractors may request contract modifications for equitable adjustments to compensate for increased costs or time due to changes in State law applied by the procurement unit
-
Deadline for filing written notice of contract claims extended from 30 days to 60 days, and protest decision timeline extended from 60 to 90 days before a protestor may deem no response as a denial
-
Provisions previously applying only to construction contract claims now apply to all procurement contracts, including requirements for written explanations within 90 days of submitting notice
-
Prior to payment on claims, contractors must provide certification from a senior officer that the claim is made in good faith, supporting data is accurate, and the amount requested is what they believe is owed