MD SB596
Bill
Status
2/5/2026
Primary Sponsor
Katie Hester
Click for details
AI Summary
-
Large load customers (commercial/industrial users with at least 25 megawatts monthly demand and over 80% load factor) purchasing surplus interconnection capacity are exempt from obtaining a certificate of public convenience and necessity
-
Large load customers must provide interconnection capacity for at least 25% of their load through behind-the-meter storage, new energy storage facilities, carbon-free assets, or demand response before connecting to the electric system
-
Customers providing 100% of their load capacity and paying prevailing wage receive prioritized processing for load studies, interconnection, and permitting
-
Public Service Commission must establish a Demand Response Program offering large load customers either 6 nonconsecutive 4-hour periods or 10 nonconsecutive 10-hour periods of load management annually, with 24-hour advance notice and 30-minute final notice requirements
-
Maryland Energy Administration must complete a study of surplus interconnection potential at all state generating facilities by December 31, 2026, and share results with data center developers to encourage use of surplus capacity
Legislative Description
Large Load Customers - Electric System Interconnection and Demand Response Program
Rules and Regulations
Last Action
Hearing 3/05 at 1:00 p.m.
2/24/2026