HB 4892 Summary
-
Mandates that construction contracts for transportation projects include progress payments to contractors, changing the requirement from optional to mandatory.
-
Requires the Department of Transportation to pay contractors within 14 days of a monthly submission date for completed items without exceptions, and within 75 days for final payments after project completion.
-
Imposes a penalty of 0.75% monthly interest on any progress or final payment not made within 75 days of the due date, applied each month the payment remains outstanding.
-
Establishes a dispute resolution process allowing contractors to raise exceptions to payment offers within 45 days, while requiring the department to pay the offered amount within 75 days regardless of pending disputes.
-
Applies to all construction contracts entered into after January 1, 2014, and requires the Department of Transportation to adopt uniform prompt payment practices complying with these provisions.
Legislative Description
State financing and management; purchasing; payment of transportation construction contracts by state transportation department within certain time frame; require. Amends sec. 7a of 1964 PA 286 (MCL 247.807a) & adds sec. 7b.
State financing and management, purchasing
Last Action
Printed Bill Filed 07/19/2013