Amends the 1969 Public Service Commission gas safety standards act to add provisions prohibiting wind turbine construction near gas pipelines.
-
Prohibits construction of wind turbines with nameplate capacity exceeding 100 kilowatts within a distance from gas pipeline lines that is less than or equal to 2 times the height of the wind turbine.
-
Applies the wind turbine setback requirement to distribution lines, gathering lines, and transmission lines carrying natural gas.
-
Clarifies that the wind turbine restriction applies to all persons subject to the act, including those engaged in interstate commerce, with limited exemptions for federal energy regulatory commission-regulated entities.
-
Defines distribution lines, gathering lines, and transmission lines based on their function in the gas pipeline system, including operational specifications and connection points.
Legislative Description
Energy; alternative sources; siting of large wind turbines; prohibit within certain distance of a gas line. Amends title & sec. 10 of 1969 PA 165 (MCL 483.160) & adds sec. 10a.
Energy: alternative sources
Last Action
Printed Bill Filed 01/28/2015