AI Summary
- Requires applicants seeking to construct high-voltage transmission lines to propose at least two routes to the Public Utilities Commission
- Prohibits designation of any proposed route as a "preferred route" in the application process
- Requires all proposed routes to be numbered and designated as alternatives rather than ranked by preference
- Applies to route applications filed on or after the day following final enactment of the bill
- Amends Minnesota Statutes 2012, section 216E.03, subdivision 3
Legislative Description
High-voltage transmission line routing process regulated, and designation of a preferred route prohibited in the permitting process.
Last Action
Secretary of State Chapter 221 05/09/14