AI Summary

  • Requires retainage (money reserved from progress payments) on building and construction contracts to be held in an interest-bearing escrow or trust account with a Minnesota bank or trust company

  • Limits retainage to a maximum of five percent of each progress payment unless the contract specifies otherwise

  • Mandates release of all retained funds plus accrued interest within 30 days after substantial completion of work to the persons from whom retainage was reserved

  • Defines "substantial completion" as the point when work is sufficiently completed so the owner can occupy or use it for the intended purpose

  • Excludes contracts for professional services as defined in Minnesota Statutes sections 326.02 to 326.15

Legislative Description

Building and construction contracts retainage held in escrow requirement

Last Action

Withdrawn and re-referred to Jobs, Agriculture and Rural Development

3/13/2013

Committee Referrals

Jobs, Agriculture and Rural Development3/13/2013
Judiciary2/28/2013

Full Bill Text