MN SF1898

Bill

Status

Passed

5/20/2016

Primary Sponsor

Daniel Sparks

Click for details

Origin

Senate

89th Legislature 2015-2016

AI Summary

  • Requires prime contractors and all subcontractors to pay undisputed subcontractor and material supplier invoices within 10 days of receipt.

  • Imposes interest penalty of 1-1/2 percent per month on undisputed amounts not paid on time, with a minimum penalty of $10 for unpaid balances of $100 or more.

  • Awards costs, disbursements, and attorney fees to any party that prevails in civil action to collect interest penalties.

  • Allows prime contractors or subcontractors to suspend work if undisputed payment is not received within 10 days.

  • Caps retainage (money withheld from progress payments) at 5 percent of each payment unless contract specifies otherwise, and permits owners to reduce or eliminate retainage if work progresses satisfactorily.

  • Effective August 1, 2016, applying to building and construction contracts executed on or after that date.

Legislative Description

Building and construction contracts progress payments and retainages modifications

Last Action

Secretary of State Chapter 133 05/19/16