AI Summary

  • Public contracting agencies must release retainage or final payment to prime contractors within 45 days of substantial completion of work.

  • After substantial completion, agencies may withhold no more than 150 percent of the value of incomplete or defective work, which must be paid within 45 days after completion.

  • Public contracting agencies may reduce or eliminate retainage if work is progressing satisfactorily, at the agency's discretion.

  • "Substantial completion" is defined by reference to Minnesota Statutes section 541.051, subdivision 1, paragraph (a).

  • The requirements apply to agreements entered into on or after August 1, 2018.

Legislative Description

Release of retainage required within certain time period.

Last Action

Authors added Dettmer.

3/28/2018

Committee Referrals

State Government Finance3/26/2018
Government Operations and Elections Policy2/20/2018

Full Bill Text