Allows public utilities to petition the Public Utilities Commission for an advance determination of prudence for energy storage systems owned and operated by the utility.
-
Petition must include project description, reasonableness evidence, discussion of alternatives, implementation schedule, cost estimate, efforts to ensure lowest costs, grid interaction information, and specific project goals such as frequency/voltage control, transmission congestion mitigation, emergency power supply, renewable energy curtailment reduction, and peak power cost reduction.
-
Commission must allow oral and written comment on petitions and make a final determination within six months of filing, providing findings in support and prohibiting approval unless the project provides net benefits to ratepayers.
-
Utilities may recover approved project costs through the next rate case or a commission-approved rider, with the commission able to accept, modify, or reject costs regardless of prior prudence determinations.
-
Return on investment for rider-approved projects must match the rate approved in the utility's last general rate case unless the commission determines a different rate of return serves the public interest.
Legislative Description
Energy storage systems advance determination of prudence authorization
Last Action
Withdrawn and returned to author