AI Summary
-
Appropriates $487,125 from the general fund in fiscal year 2023 to the commissioner of transportation for regrading work on Trunk Highway 74 in Winona County.
-
Funds will be used to regrade 3.9 miles of marked Trunk Highway 74 north of Elba to Winona County State-Aid Highway 30 using Otta seal.
-
Appropriation covers design, engineering, construction, and acquisition of right-of-way for the project.
-
Designated as a onetime appropriation available until June 30, 2025.
Legislative Description
Winona County; Trunk Highway 74 segment regrade funding provided, and money appropriated.
Last Action
Introduction and first reading, referred to Transportation Finance and Policy