Loading chat...

MN HF5097

Bill

Status

Introduced

3/21/2024

Primary Sponsor

Patty Acomb

Click for details

Origin

House of Representatives

93rd Legislature 2023-2024

AI Summary

HF 5097 Summary

  • Public Utilities Commission must initiate a proceeding by September 1, 2024, to establish generic standards for allocating utility costs to upgrade distribution systems and increase hosting capacity for distributed generation facilities (maximum 10 megawatts).

  • Cost allocation standards must ensure fair pro rata cost-sharing among distributed generation project owners based on expanded capacity utilized, with provisions for minimum upgrade thresholds and refunds for overpayments.

  • Public Utilities Commission must establish a new full-time interconnection ombudsperson position to assist applicants, track disputes, facilitate dispute resolution, review utility policies, and prepare reports on interconnection issues.

  • Electric utilities must assess a $35 surcharge on each interconnection application filed by distributed generation facility owners in Minnesota, remitted monthly to the Public Utilities Commission.

  • Surcharge revenues fund the ombudsperson position through a special revenue account, with the commission authorized to adjust the surcharge annually to ensure adequate funding and maintain appropriate reserves.

Legislative Description

Initiation of proceeding at Public Utilities Commission regarding cost allocation of distribution system upgrades required, interconnection ombudsperson position at Public Utilities Commission established, and interconnection applications surcharge established.

Last Action

Introduction and first reading, referred to Climate and Energy Finance and Policy

3/21/2024

Committee Referrals

Climate and Energy Finance & Policy3/21/2024

Full Bill Text

No bill text available