HB 659 Summary
-
Authorizes sewer districts to enter into design-build contracts for projects exceeding $1 million, combining design and construction services under a single contract.
-
Requires sewer districts to establish written procedures for prequalifying design-build contractors before proposals are accepted, including criteria for contractor evaluation and contract award based on best overall value.
-
Mandates public advertisement in newspapers of general circulation once weekly for two consecutive weeks, and requires minimum two responsive submissions or the project must be readvertised.
-
Requires sewer districts to retain an independent architect or engineer to assist with project planning, design criteria package development, proposal evaluation, and contract administration; prohibits this professional from participating as the design-build contractor.
-
Establishes bonding and insurance requirements including payment bonds covering design services, professional liability insurance for design service providers, and licensing requirements for architects, engineers, and land surveyors under Missouri law.
Legislative Description
Authorizes the St. Louis Metropolitan Sewer District to enter into a design-build contract for a construction project exceeding $1 million
Last Action
HCS Voted Do Pass (H)