AI Summary
-
Requires qualified utilities (municipal utilities, electrical corporations, and rural electric cooperatives) to approve use of their transmission or distribution systems for renewable energy contracts within 60 days of receiving a customer request, subject to credit requirements
-
Contract customers must have a minimum annual peak demand of one megawatt to be eligible, though multiple metered locations may be aggregated to meet this threshold
-
Qualified utilities must file a tariff with the commission or governing body by November 28, 2015, establishing rates for administrative costs, distribution service, transmission service, generation capacity service, and supplemental energy service
-
Contract customers are responsible for incremental delivery costs from renewable energy facilities to the transmission system, and utilities are not liable for costs related to customer default
-
Environmental attributes associated with renewable energy facilities remain the property of the facility owner unless otherwise specified in a contract
Legislative Description
Establishes criteria for renewable power purchase agreements
Last Action
Second Read and Referred S Commerce, Consumer Protection, Energy and the Environment Committee
3/10/2015