MO SB1286
Bill
AI Summary
-
Political subdivisions must approve or deny permit applications for new construction, repair, or renovation of residential, commercial, or industrial buildings within 30 calendar days
-
Applications not responded to within 30 days are automatically deemed approved, authorizing the applicant to proceed with construction
-
Denials must be in writing with specific reasons, including citations to violated code provisions or detailed explanations for rejecting work stamped by certified design professionals
-
Applications denied as incomplete must include written reasons, and applicants receive 10 calendar days to resubmit with the requested information
-
Political subdivisions cannot add new denial reasons on resubmitted applications that were not specified in the original denial
Legislative Description
Modifies provisions relating to local permitting applications
Last Action
Hearing Conducted S Local Government, Elections and Pensions Committee
3/9/2026