MS HB1217
Bill
Status
2/23/2016
Primary Sponsor
Richard Bennett
Click for details
AI Summary
-
Requires municipalities and county boards of supervisors to prepare a timeline for moving public utilities' underground utilities whenever a construction project is permitted.
-
Gives utilities 60 days to review and comment on the proposed timeline for underground utility removal.
-
Requires municipality or county and utility to enter into a written agreement within 60 days after the review period, with failure to do so triggering a $500 per day penalty payable to the municipality or county.
-
Imposes a $500 per day penalty against utilities that fail to meet deadlines specified in the removal agreement, payable to the municipality or county until compliance is achieved.
-
Requires municipalities or counties to provide utilities 30 days written notice before levying any penalties under this act.
Legislative Description
Agreement pertaining to moving utility lines; authorize counties and cities to enter into with utilities for certain permitted projects.
Last Action
Died In Committee
2/23/2016