MS HB1262
Bill
Status
2/23/2016
Primary Sponsor
Mark Baker
Click for details
AI Summary
-
Requires railroads and public entities to reasonably accommodate each other when public improvement projects conflict with railroad operations or facilities, including timely issuance of easements, work permits, and licenses.
-
Mandates railroads issue necessary permits within 60 days of engineering documentation submission from the Department of Transportation, and public entities issue permits to railroads within 60 days of documentation submission.
-
Requires both parties to fully comply with permit terms unless 30 days advance notice is provided for changes to timing, duration, or cancellation; failure to comply constitutes prima facie evidence of unreasonable delay.
-
Establishes expedited court procedures allowing initial hearings within 5 days of complaint filing, with court decisions required within 10 days; courts may order permit issuance, enforce permit terms, and award attorney's fees and costs.
-
Amends Section 65-1-69 to clarify that railroad-highway crossing projects must comply with the new accommodation requirements and prohibits unreasonable delays in construction.
Legislative Description
Public improvement projects; require public entities and railroads to reasonably accommodate each other in a timely fashion.
Last Action
Died In Committee
2/23/2016