Loading chat...

MS HB1859

Bill

Status

Failed

3/27/2024

Primary Sponsor

Jeffery Harness

Click for details

Origin

House of Representatives

2024 Regular Session

AI Summary

  • Appropriates $1,800,000 from the State General Fund to the Board of Supervisors of Jefferson County for fiscal year 2025 (July 1, 2024 - June 30, 2025)
  • Funds cover Phase I costs including route location study, geotechnical investigation, design engineering, and environmental documentation for reconstructing a portion of McBride Road to state route standards
  • Allows Jefferson County to pursue federal funding for the construction phase of the project following completion of Phase I
  • Takes effect July 1, 2024

Legislative Description

Appropriation; Jefferson County for Phase I of project to reconstruct portion of McBride Road.

Last Action

Died In Committee

3/27/2024

Committee Referrals

Appropriations A3/14/2024

Full Bill Text

No bill text available