MT HB672
Bill
Status
5/5/2025
Primary Sponsor
Courtenay Sprunger
Click for details
AI Summary
-
Department of Transportation pays 75% of utility relocation costs for highway construction, 100% for publicly owned water/sewer facilities with 500 or fewer service connectors, and 85% for those with 500-1,000 connectors
-
Department must provide preliminary notice to utilities whose facilities must relocate for highway projects and may incrementally reduce reimbursement to 0% for facilities not relocated in a reasonable time, with reductions beginning no earlier than 90 days after notice
-
Department may remove utility or nonutility facilities that fail to relocate after reasonable written notice or that were not installed in accordance with permits
-
Department and its contractors receive limited liability protection for facility removals carried out in compliance with the law, except for willful misconduct, gross negligence, or certain statutory violations
-
Department must consult with the transportation interim committee, utility companies, telecommunications providers, and highway contractors before proposing rules under this section; effective January 1, 2026
Legislative Description
Generally revise Montana department of transportation’s utility relocation process
Rule Making
Last Action
Chapter Number Assigned
5/8/2025