Lower Cape Fear Water and Sewer Authority is authorized to use the design-build method of construction for water projects within its service area, notwithstanding existing state procurement statutes.
-
Authority must prequalify and solicit at least three design-build teams to bid and receive at least three sealed proposals for each project, with proposals not requiring submission of detailed design solutions.
-
Authority must interview at least two of the design-build teams that submit proposals and award the contract to the best qualified team based on project completion time, compliance with G.S. 143-128.2, and project cost.
-
Authority may proceed with fewer than three proposals if the project has been publicly advertised for a minimum of 30 days and three proposals are not received.
-
Act becomes effective upon passage and expires December 31, 2015.
Legislative Description
Lower Cape Fear Design-Build
Last Action
Ref To Com On State and Local Government