Amends Section 28-05-09 to clarify that notice of pendency is not required for actions to enforce construction liens or miner's liens.
-
Modifies Section 35-27-25 to require lienholders to commence suit and record a lis pendens within 30 days of receiving written demand from the owner, agent, or contractor, or forfeit the lien.
-
Establishes a 3-year deadline from the date of recording for a lienor to commence an action and record a lis pendens to enforce the lien, after which the lien is deemed satisfied.
-
Specifies the 30-day requirement applies regardless of delivery method with no extensions permitted, and requires the demand notice to inform the lienor of forfeiture consequences.
-
Applies the amendments to construction liens of record on the effective date while not extending enforcement time for existing liens.
Legislative Description
Actions for construction liens and miner's liens; and to provide for application.
Last Action
Signed by Governor 04/11