ND HB1181
Bill
Status
4/13/2017
Primary Sponsor
Nathan Toman
Click for details
AI Summary
-
Wind option agreements become void and terminate if a certificate of site compatibility or conditional use permit and an active transmission interconnection request are not obtained within five years after the agreement commences.
-
Energy rights owners may terminate void wind option agreements by providing certified notice to the property owner and filing the notice with the county recorder; termination is effective five years after the agreement commenced.
-
Wind easements are presumed abandoned if 36 consecutive months pass without construction or operation of the wind farm facility, and the energy rights owner may terminate the easement with a 60-day written notice unless the easement owner files a written objection.
-
Wind energy leases are void if site compatibility certification or conditional use permit and an active transmission interconnection request are not obtained within five years after the lease commences.
-
Wind leases are presumed abandoned after 36 consecutive months of no construction or operation, and energy rights owners may terminate with a 60-day notice unless the leaseholder files a written objection within that period.
Legislative Description
Termination of wind option agreements, wind easements, and wind energy leases.
Last Action
Signed by Governor 04/13