ND HB1087
Bill
Status
3/11/2019
Primary Sponsor
Agriculture Committee
Click for details
AI Summary
-
Exempts agricultural dikes less than two feet in height from professional engineer requirement and permitting process.
-
Requires state engineer to complete initial review of dam, dike, or other device applications within 45 days, except in unique or complex situations.
-
Requires water resource board to review applications within 45 days and forward approval to state engineer; board silence equals no objections.
-
Allows state engineer to issue temporary permits for dikes, dams, or other devices in emergency situations.
-
Establishes that constructing dams, dikes, or devices capable of retaining more than 50 acre-feet of water (or 25 acre-feet for medium or high-hazard dams) without a permit is a class B misdemeanor and creates liability for all damages caused.
Legislative Description
A permit to construct or modify a dam, dike, or other device.
Last Action
Signed by Governor 03/08
3/11/2019