ND HB1385

Bill

Status

Introduced

1/13/2025

Primary Sponsor

Cynthia Schreiber-Beck

Click for details

Origin

House of Representatives

69th Legislative Assembly

AI Summary

  • Department of Water Resources must complete final decisions on dam, dike, and water device permit applications within 120 days of receiving a completed application; permits are automatically approved with no conditions if the deadline is missed

  • Removes the "unique or complex situations" exception that previously allowed the department to extend the 45-day initial review period for dam and dike applications

  • Water resource boards must decide complaints about dams, dikes, or drainage within 120 days; the department must decide appeals within 120 days or the appeal is automatically denied

  • Drainage permit applications must be referred to the appropriate water resource district within 120 days; if the department fails to refer within that period, the district may approve the application with reasonable conditions

  • Amends four sections of North Dakota Century Code (61-16.1-38, 61-16.1-53.1, 61-32-03, and 61-32-08) to establish consistent permit processing deadlines across water resource permitting

Legislative Description

Deadlines for permits issued by the department of water resources.

Last Action

Second reading, failed to pass, yeas 0 nays 92

2/5/2025

Committee Referrals

Energy and Natural Resources1/13/2025