- Expands North Dakota Public Service Commission's siting authority to include data centers alongside existing regulation of energy conversion facilities and electric transmission facilities
- Requires data centers to obtain a certificate of site compatibility before construction, following the same application and review process as energy facilities
- Defines "data center" as structures containing electronic equipment for processing, storing, and transmitting digital information or conducting data mining, including servers, storage systems, and networking equipment
- Mandates data centers comply with American National Standards Institute design best practices and state fire code requirements
- Establishes penalties for non-compliance including class A misdemeanor charges and civil penalties up to $10,000 per day per violation, with a maximum of $200,000 for related violations
Legislative Description
Authorization for the public service commission to regulate the siting compatibility for data centers; and to provide a penalty.
Last Action
Withdrawn from further consideration